on 07-16-2012 8:53 AM
Hi All,
Good morning.
I created one project and done budgeting (CJ30) for this project. then i transferred some amount of budget(CJ34) from 1 WBS to 2 WBS in same project.
Now i want to delete this project, for this action we should reset the BUDG status of Project. So i transferred the same amount from WBS 2 to WBS1 in CJ34 , and in CJ30 i delete the all budget and saved it. Now when I am running the T code OPSX for that project BUDG status is not being reset.
Please help.
Thanks
Dear sonal....,
Please follow the following steps(post making the budget balances zero)-
a) Deactivate availability control using TCode-CJBW.
b) Reconstruct Project Info d/b using TCode-CJBN.
c) Reset the BUDG status using TCode- OPSX.
Please confirm if it worked or not.
Thanks and Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sonal,
You can put deletion flag on project.
For deletion flag follow- Edit->Status->deletion flag->set.
Deletion of project is not preferred. Put deletion flag instead.
See this-
1. For deleting project-http://scn.sap.com/thread/880572
2. For deleting WBS-http://scn.sap.com/thread/1416611
3. For Rules of engagement-http://scn.sap.com/docs/DOC-19331
Regards,
Pranav
Message was edited by: Pranav Trivid
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.