Hi all,

We have ECC-PI-SNC Integration.

In standard Purchase Order Processing scenario, in the reciever SNC system we are getting the Application Error : Recepient party is invalid.

Could this be a configuration issue?

Regards,
Aditi

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Aditi,

I am facing the same problem as mentioned by you. Have the issues got resolved? If yes can you please share the procedure you have followed.

I have created a new thread for it. You can click below link to get more info related to my issue.

http://scn.sap.com/thread/3303703

Thanks in advance.

Pratyusa

Former Member
0 Kudos

Hi Aditi,

Check the below link.

http://scn.sap.com/thread/3300011

Thanks,

Satish.

Former Member
0 Kudos

Hi Satish,

The link you have provided in the previous post is created by me in SNC forum. That link contains all the possible configuration mistakes which can lead to such error.

I found the solution for the error

" The error was not from PI perspective. The error is due to improper data loading in SCM server. There was inconsistency in data updation into SCM server. While the data uploading into SCM server are done again and BP are created in SCM server the issue got resolved."

Thanks

Pratyusa

MichalKrawczyk
Active Contributor
0 Kudos

Hi,

>>>Could this be a configuration issue?

it certainly looks like that,

go through the guide once more and check blogs on sdn on the same topic,

Regards,

Michal Krawczyk