While I am trying to look at Gantt chart from CJ20n an information message shows up " Date not in the factory calendar (future)". Then I checked the factory calendar settings in SCAL, there it is shows the calendar is valid till 2015. Can anyone help me on this?
Thanks
Prabhu
Hi,
What is the date which you have filled in the project. If its previous date check for previous year also.
Check again and schedule the project, to get the start and end date.
CHeck which factory calendar is maintained in that particular object (WBS, Network).
Might be possible there is different factory calendar maintained in project definition and other object, and probably you are looking for some other.
Regards
Shubham
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I dont think there is any setting in SPRO, but maintaining different factory calendar should not give the error.
Probably you might be missing the factory calendar which is there in the project.
Check through CN41N, what all the factory calendars are maintained in whole project (all WBS, networks, etc). Then check their validity in SCAL.
Or else share screenshot of all.
Thanks
Shubham
Hi Prabhu,
For solving this error, All possible solution has been provided to you in this thread.
The only reason behind your error (CO500) is unavailability of calenders for scheduling dates.
1. Check dates of each activity & WBS & project.
2. Check corresponding calenders for availability on that date.
Or run a test cycle for chosen calender and a date within its range.
Regards,
Pranav
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.