on 07-11-2012 6:28 AM
Hi,
Valuated project stock will updates Moving average price after GR/GI?
sudheer
It will update only the Moving average price of the project stock, you can check it with transaction MBBS.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi sudheer,
See rules of engagement before posting any question on this forum. Link is-
http://scn.sap.com/docs/DOC-19331
Regards,
Pranav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Frame your question properly and explain the issue in detail for others to understand it and answer it. Seems like you do not have enough time to frame the question and post it.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI Gokul & all,
One of my client needs a z report in which he needs to view the materials procurred against the WBS element with the PO price difference between 2 dates. Generally we can check the price movement difference of PO in ME1P. But he needs to view by providing the wbs element in the selection screen. May i know from which table i can fetch the PO difference price along with wbs element. Can you please share the logic so that I can provide to my Abaper to develop the Z report.
Thanks in advance,
Regards,
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.