cancel
Showing results for 
Search instead for 
Did you mean: 

inspection type 02

former_member223028
Participant
0 Kudos

Hi dears

i was activated 02 type inspection

so after issue the material against order system creating inspection lot

my doubt is that if the lot is rejected what is the next process wether this material will come back in ware house or  a new new inspection lot was trigger

what is the next step in this production order

Thanks in advance

Abu

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

I hope you are talking about the 122 mvt in the qa11/12 inspection lot.

This is "RE return to order"

means order only show  ->  production order qty -return qty = delivered qty.

means order opens for the returns qty.

former_member223028
Participant
0 Kudos

hi sujit ji

i was telling 261 movment type .when i issue a material against a process order system creating lot

but if i reject the rr on inspection processing ..what is the next step

pls guide me

Abu Fathima

Former Member
0 Kudos

If its against the order then logically 02 should be created with the reference of odder .When you do RD then material issue will get open by that much qty.Logic should remain same.means when you reject the same its allow you to do 261 again for rejected qty.

anand_rao3
Active Contributor
0 Kudos

Hello Abu,

  1. 02 inspection type lots are stock irrelevant and barely has a significance.
  2. These do not have stock posting facility.
  3. If you find any rejection here, you need to carry out steps separately to block the stock.
  4. If the material is consumed, (depending upon your customization) you should reverse the stock with 262 and then transfer the stock to block stock for further analysis.

Regards

Anadn

Answers (1)

Answers (1)

former_member223028
Participant
0 Kudos

Hi dears

Any comments please

Abu fathima