Hi,

In my scenerio we have activated Fund center functionality.

If we activate fund center functionality we can't do the budgeting through PS, can we atleast do the Project cost plan in CJ40?

Please do commment, I will appreciate your valuable feedback.

Regards

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Why don't you run CJ40 and check for yourself if the system allows you to do the cost planning? As far as i know activation of fund center should not disallow you from doing the cost planning through CJ40.

Check and revert.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Kailas,

As far as I know you can do it.

Run a test cycle and check it.

Regards,

Pranav