Dear All ,

Please need ur valuable suggestion for the below scenario:

Customer asks for X(FG) material now plant manufactures semifinished

product and send its to his vendor where he will make it FG and from there

itself he delivers the material to customer .Now how we can map this scenario.

Thank and Regards

Accepted Solutions (1)

Accepted Solutions (1)

Shiva_Ram
Active Contributor
0 Kudos

It looks this can be achieved using third party sales subcontracting process. As per the thread http://scn.sap.com/thread/593508 it is available in EHP 5.

I also recommend you to post in materials management forum.

Regards,

former_member317998
Participant
0 Kudos

Hi shiva ,

Thanks very much ,it was very helpfull

Former Member
0 Kudos

Dear S K,

this is a standard scenario in SAP.

Delivery by an external supplier(THIRD PARTY ORDER PROCESSING).

http://wiki.sdn.sap.com/wiki/display/ERPLO/Third+Party+order+processing+in+Sales.

Thanks

R N S