User status change of activity after project release

Former Member
0 Kudos

Hi,

    When i release the project definition, complete project gets release, when i go for activity confirmation thru CN25 system displays error of with message no.BS042 about the user status is still in CRTD stage. System status appear as REL but when clicked at the user status the system status is stil in CRTD stage after manually selecting REL for particular activity the system then allows for confirmation

Image 01

Image 02 - User status of same activity

After changing the above status from CRTD to REL manually system then allowas for activity confirmation

Kindly suggest the appropriate solution

Best Regards,

Nitesh H Panchal

Accepted Solutions (0)

Answers (1)

Answers (1)

schneidertho
Advisor
Advisor
0 Kudos

Hi Nitesh,

as far as I recall user status are not inherited automatically in PS. I think you have to trigger that manually. Or you need to go to the activity and change the user status there. (I am not sure about the business requirement you want to achieve with the user status)

Best regards