When i release the project definition, complete project gets release, when i go for activity confirmation thru CN25 system displays error of with message no.BS042 about the user status is still in CRTD stage. System status appear as REL but when clicked at the user status the system status is stil in CRTD stage after manually selecting REL for particular activity the system then allows for confirmation
Image 01
Image 02 - User status of same activity
After changing the above status from CRTD to REL manually system then allowas for activity confirmation
Kindly suggest the appropriate solution
Best Regards,
Nitesh H Panchal
Hi Nitesh,
as far as I recall user status are not inherited automatically in PS. I think you have to trigger that manually. Or you need to go to the activity and change the user status there. (I am not sure about the business requirement you want to achieve with the user status)
Best regards
Thorsten
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
10 | |
5 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.