on 07-09-2012 11:02 AM
Hi there
I have a Confirmation which has the status “Error in process”. In the bbp_pd says that there is a problem with the transfer.
And the idoc has the status 51 quoting that the WBS is not allowed.
When I check the wbs in the ECC transaction we05, it has the status REL
Could please anyone help me to find out where the issue comes from?
Thanks
HI Carl,
Please check with the Backend Team and get the error related to the IDOc ( as the confirmation is posted in the backend via IDOc's)
I assume that this is related to the GL Account, not sure though.
Hope this helps!!
BR// 420
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please chceck Tcode RZ20 and under Enterprise Buyer Monitors select it and check the Error for your Confirmaton. Usually this might be problem with the data you are using. Kindly cross check the data you are using. This might me the master data issue
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You should re-run that idoc using Txn BD87. Can you do that? Let me know if it works for you.