I have a question regarding VA32, if anyone can suggest me.

One of our customer is not sending us 'cumulative received qty' in the schedules (DELINS), so the value sits in 'cumulative transit qty'.

After the schedule arrives, Cumulative Received qty is zero and entire value is in 'cumulative qty Transit'.... until we sends the 1st delivery to customer.

The effect is, there is no open qty in scheduling agreement(until the 1st delivery), so no value in MD04.

Is there any program, which we can run in the night, that moves the Cumulative Transit qty to cumulative received qty ???

Regards,

Jat

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Is the [Propose CRQ] button available when you look at the delivery schedule on VA32?

If the customer does not provide a Cumulative Quantity Received, by leaving the field blank (not 0), SAP will calculate the Cumulative Quantity Received based on the Cumulative Issued Quantity.

The Propose CRQ button on VA32 Delivery schedules basically does the same thing, and is useful for manually entered Releases.

Cum

0 Kudos

I am pressing propose CRQ but nothing is happening so tell the complete process to updated this received quantity. Don't tell wrong process, if you don't know the process so don't involve in this.

thanks

Lakshmipathi
Active Contributor
0 Kudos

Thanks for coming to SAP Community for answers. Please post your question as a new question here:
https://answers.sap.com/questions/ask.htmlSince you're new in asking questions here, check out our tutorial about asking and answering questions (if you haven't already), as it provides tips for preparing questions more effectively, that draw responses from our members. Please note, that your post here won't be answered.