on 07-06-2012 8:52 AM
Hello All,
Requirement is that my client wants to see Gant chart for Basic dates, Forecast dates and dates of the simulation version of the same project (so means 3 set of schedules) in a single gantt chart. Is this possible?
Regards,
Jatinder
Dear Jatinder,
Best Regards,
Edna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello All,
I am able to get 2 Simulaton versions in single gant chart, by selecting VErsion Data in DB Profile,(T code - CN47). But now in the corresponding gantt chart, i see bars for both versions wth same color, is there any way to see the bars of different colors in different colors??
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.