Hello All,

I have a question on Display Original Schedule in Planning Board.

Clicking on OPTIONS in planning board --> Planning Board --> Diagram Area --> Select B ORIGINAL Schedule is Displayed,

With this i get a grey bar for the original schedule, this is the 3rd bar along with the 2 bars (Basic and Forecast bars), But when i make changes to the basic/Foirecast dates and save the project, and again open the project the GREY BARS disappears? why so? Is this grey bar valid only for the duration for which the project is open??

Regards,

Jatinder

Accepted Solutions (1)

Accepted Solutions (1)

0 Kudos

Dear Jatinder,

Yes, the bar of original schedule is only valid for the duration for which the project is open. As once

the data is saved, the 'original' dates on the database are changed.