Hello All,
I have a question on Display Original Schedule in Planning Board.
Clicking on OPTIONS in planning board --> Planning Board --> Diagram Area --> Select B ORIGINAL Schedule is Displayed,
With this i get a grey bar for the original schedule, this is the 3rd bar along with the 2 bars (Basic and Forecast bars), But when i make changes to the basic/Foirecast dates and save the project, and again open the project the GREY BARS disappears? why so? Is this grey bar valid only for the duration for which the project is open??
Regards,
Jatinder
Dear Jatinder,
Yes, the bar of original schedule is only valid for the duration for which the project is open. As once
the data is saved, the 'original' dates on the database are changed.
Best Regards,
Edna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.