on 07-05-2012 2:10 PM
Hi,
I created a work center with capacity 10 people, and working for 8 Hrs a day starting 9 AM and ending 5 PM without any breaks.
Accordingly when i assign this work center to NWP/Activity system calculates start and end date, as calculaton key entered is 1.
Now i want one of the person to work overtime for one day, i.e he will work from 5PM till 10 PM, how to add this in the system. I know we can extend work center capacity, but can we do this on CJ20n directly?
Regards,
Jatinder
No, you can not do same in CJ20n.
Better way is to make it as seperate work center if its capacity differs from others.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Jatinder,
Here are some notes related to Workforce Planning. Hope these helps.
185183 Create assignment, show availability
360648 Guide to the scheduling of splits for persons
371893 Missing working time information on persons
543362 Consulting: Workforce Planning
Best Regards,
Edna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
109 | |
15 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.