on 07-05-2012 10:55 AM
Hello Experts,
Transporting a number of requests (one by one) from Dev to Prod I see yellow status for the requests. It says "request is ready for import again" although RC is 0 (green). Why does it show yellow status then?
Even though the requests are shown with yellow sign, they are imported. I can check respective objects and see the changes that are brough by the requests.
SAP_BASIS | 730 | 0007 | SAPKB73007 |
SAP_ABA | 730 | 0007 | SAPKA73007 |
PI_BASIS | 730 | 0007 | SAPK-73007INPIBASIS |
ST-PI | 2008_1_710 | 0006 | SAPKITLRE6 |
SAP_BW | 730 | 0007 | SAPKW73007 |
Kind Regards,
Kirill
Hello Kirill,
there's no error here, the yellow light does not mean warnings on this case:
Yellow triangle --> Request is ready for import again
Green check --> Request already imported
There's an option you select to make the request available to be imported again, hence this status.
When importing the transport, if you leave the "Leave Transport Request in Queue for Later Import" unchecked then you will not get the "yellow triangle" status.
Please also review the online documentation for more detail:
http://help.sap.com/saphelp_nw70/helpdata/en/5c/d21880fe3c11d2b461006094b9ea64/frameset.htm
I hope this information clarifies.
Best regards!
Tomas Black
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.