on 07-04-2012 4:22 PM
hi fortain,
can you jsut put the screen shots of your budget profile and availability control settings and the error message you are getting.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
ho fortain,
do one thing in cj31 when you are allocating the budget before check for error go to extras tab >>> avaialaibility control >>>> activate and then check whether its working or not.....
and also go to spro >> project system >> cost >> budget >> stipulate default budget profile for project definition and check whether you have assign the correct budget profile there.
hi fortan,
it is analysis report it will gives you all the details of your budet . just click on + button in the customizing settings it will show you which type of budget profile you are using and whether availibilty control is active or not.. i told you to click on activate button and then save your budget. follow the steps i mentioned in my previous profile and try to save your budget.
hi fortain,
this field should not be come in grey i think you have miss some config settings. iws this is the first project or you have already created some other projects with the same settings.
just check when you are creating the wbs element in control tab correct budget profile is coming. or just check the tables
The program control table TRWCI (in which the installed components are stored) must contain the COFC entry (Controlling Funds Control).
the TRWCA table contains the same components (fiscal year-related) as the TRWCI table. You can use this table to deactivate specific components for certain fiscal years. In the TRWCA table, the COFC component should be active until the year 2050. for more information just follow this links
http://help.sap.com/saphelp_wp/helpdata/en/bb/e4a63730d5432ce10000009b38f842/content.htm
Transaction CJ31 is the display transaction I think it might be correct to have that option greyed. In CJ30 is available.
This is not the first project, we have created many other projects with the same settings (at least we haven't detected any differences yet).
I've check tables TRWCI and TRWCA and they seem to be ok:
hi fortain,
first check you budget profile (ops9). in there check activation type might be there you take 0 instead of 1 or 2.
if it is ok. then go to t-code cjbw and deactivate availability control (cjbw) there and then run cjen it will reconstruct the databse tables for project info and then activate the availability control ( cjbv) and then again run the project construct info (cjen). it will work also refer this link
http://help.sap.com/saphelp_srm40/helpdata/en/4f/b3e739e62b714be10000000a114084/content.htm
can you please tell me which type of project your are working on.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear sulabh gupta,
At the budget profile we have the option "1 Automatic activation during budget allocation" which has been working until now.
I tried to follow the steps you told me, when running CJBW we get the message: "Availability control was not active for the following pro ..." and after all the steps we keep getting the same messages at CJBV and CJ31.
Any other idea of what could be happening?
Thanks to all
Hi Fortian,
1. Try to activate Project availability control by CJBV(Run this in Background F9).
2. Also Run CJEN for reconstruct project Info.
Regards,
Pranav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.