Planning

Former Member
0 Kudos

Hi Experts,

We are using Planning calendars as the requirement is some products should start only on Monday and some on thursdaya so we have assigned monday calendar and  thursday calendar in the product master. BY period is ticked and period type is K.in the lotsize view. planned order start date should be on either on monday or thursday.  But the sytem is not respecting and the planned order start date and is something which is not considering the planning calendar. Can anyone throw some light on to this.

Regards

Shruths

Accepted Solutions (1)

Accepted Solutions (1)

claire_yang
Contributor
0 Kudos

Hi,

You need to set flag "use period factor" in product master.

Also please apply note 1731346.

If the resource have no capacity to fulfill the order on start date in planning calendar then date will be rescheduled according to your strategy profile. You may check your resource capacity in transaction /n/sapapo/rest02.

if you need further checking, you may create an OSS.

Claire

Former Member
0 Kudos

Thank u. This problem got resolved after applying the note. Thanks

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello Shruthi,

Please check the validity of factory alendar also.

Look for the below link:

http://scn.sap.com/thread/1701866

Check the resource capacity also along with the factory calendar.

If the resource have no capacity to fulfill the order on start date in planning calendar then date will not be the same.

Once your planning calendar and factory calendar are valid the planned order should have a valid start date.

Hope this helps

Regards

Former Member
0 Kudos

Shwetha,

Actually, planning calendar is required for product. Resourcw runs for all the days in a week. there are certain products which should run only on monday and some products on wednesday. i thought planning calendar assignment in prod master wud help. but no result. any other suggestion will be appreciated.

shruths