Dear SAP experts,


We are using SRM 7.01 with backend ECC 6.05. We would like to use feature of synchronizing HR org structure in ECC to SRM. Do you guys have any hints of doing this? And also, do I need to create root org first in SRM or a root org will be created at the first time I synch the org structure from ECC to SRM?

Best regards,

John

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

hi,

When we implement HR replication from ECC to SRM, we need to ensure customizable table settings T77S0  as HRALX HRAC X Activate HR Integration

Refer: http://allaboutsapsrm.blogspot.in/2012/04/how-to-replicate-hr-org-structure-from.html#!/2012/04/how-...

Yes, you need to create the root org unit in SRM first and then replicate other nodes using tcode PFAL in ECC. You can check the structure in ECC with tcode PRMS.

-palz

Former Member
0 Kudos

hello,

Before synchronize all the users of ECC should be created in srm. ie  T code SU01.

regarding idoc replication from ECC to SRM pls check the sap note 934372.

pls refer the below link

http://scn.sap.com/thread/2042601

regards

sahil p