on 07-02-2012 8:40 AM
Hi SNC Guru's
Currently out system not allow PO changes on SNC supplier portal , when PO is already confirmed.
Can you let me know the configuration required in SNC to allow PO changes after confirmation?
Thanks
VSK
Hi VSK,
The ability to chnage a PO in SNC Web UI is defined in the config setting:
SPRO>SNC>Purchase Order > Make General Settings for Purchase Orders. Under Create Change Profile ensure the following settings:
1.Order Document Type - Purchase Order
Distribution Status - Published by Supplier
Distribution Changes for Changes - Blank
Item Status - Open
Display only Indicator - Unchecked
2. Order Document Type - Purchase Order
Distribution Status - Published by Supplier
Distribution Changes for Changes - Blank
Item Status - Partially Delivered
Display only Indicator - Unchecked
Save the settings and in next step ensure the Chnage Profile is assigned to your Business Partners.
This should resolve your issue. Confirm if it works.
Regards,
Bharath
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.