on 06-28-2012 9:37 AM
Hello Gurus,
While doing CCR in APO ,system throwing error "Schedule line without external number does not exist in R/3"against purchase
requisitions & eventually no transfer of purchase requisitions to R/3
Please let me know your inputs.
Regards
Milind
Please check if the distribution definition for External procurement is maintained or not in the configuration in APO system under publication in Basic setting for initial data transfer.
Regards,
Dharmesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Milind,
It would be helpful if you supplied the message number along with the text.
Some questions:
What version and SP level of ECC and APO do you have?
Is there any more information in the application log (CFG1)?
Is it happening for all materials?
Do you have an active integration model for purchase requisitions?
Are you using CIF Postprocessing?
Best Regards,
Mike
Hi Maclean,
Thanks for your inputs provided,Issue is resolved now.
In CFG1,I was able to see error log in detail about purchase requisitions & it was related to G/L account XXXX is missing ,some materials are having missing purchasing view etc.
Thanks again for your valuable input!
Regards
Milind
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.