on 06-27-2012 1:33 PM
Hi Experts,
SRM701 and ECC603.
Uploading contracts from ERP to SRM using the repost BBP_CONTRACT_INITIAL_UPLOAD, the contract is created but the object linkages at header and item level are missing.
What can be the issue and possible resolution for this?
Thanks,
Anubhav
Hello,
Links at header and item on contract are generated when a SRM Contract is distributed to ECC.
AFAIK there are no links generated for uploaded contracts from ECC to SRM.
The mapping between uploaded ECC contract and SRM contract is maintained in table bbpd_ctr_trns.
Regards,
Sushil.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sushil,
Thanks for the information. So how can we achieve this using custom development. Any FM or tables that can be used to update the object linkages.
I tried function modules BBP_PDH_DB_DIRECT_UPDATE and BBP_PD_SET_BE_REF (dont remember exact name) but it did not help,
Any pointers are really appriciated.
Thanks,
Anubhav
Hi Sushil,
Yes, the client has multiple back end systems. SRM will be used as a central repository for contracts. Contract created in one BE can be uploaded to SRM and then replicated to another BE.
So to track all the document history we need to maintain object linkages when the contract is uploaded from ERP to SRM.
Thanks,
Anubhav