Hi All,
I want to know about various versions in WBS. When i revised the budget at that time how can I see the revised version of WBS element. Is there any reports or entry generated. Please help me out to solve this issue.
Thanks in adavnced.
Regards,
Amit
Hi,
Tushar already eplained about the versioning very clearly. Are you creating project version? Try to see the the different version values in CN41N.
Regards,
Sudhakar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Amit,
In Project system, there are different types of versions namely simulation versions, project versions, CO planning versions and selection version.
documenting the progress of a project over time. Both quantities and values are stored in
one version to another. One can change planned values manually in every version
the costed values are retained.
background and saves project data matching certain selection criteria for retrieval
Project version can be manually created while changing the WBS, network, in the Structure/Dates information system for one or more projects. You can use the transaction CN71, CN72
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Actually there is no versioning of budget. The better way to manage this is to use supplementery budget functionality. With this functionality you cna track down the budget modifications for a WBS element.
Regards,
Mahendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.