Changing Scheduling Type in Standard NWP

Former Member
0 Kudos

Hello All,

I am able to change the scheduling profile in the operatve project from Backward to Forward etc...

But i am not able to find how do we change the scheduling profile for a standard network. any pointers will be helpfull.

Thank you.

Regards,

Jatinder

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

In put the network number and hit the return button and followed by new screen "Standard Network Change: Standard Network Header"

Staying on the screen go to menu path Edit > Scheduling. Now click on Scheduling which opens another pop up window and you can see the "Scheduling type" field, using  key F4 and select the required scheduling parameter from the drop down list and save.

Regards,

Sudhakar

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Jatinder,

I think scheduling parameters for operative network will govern once you have copied standard network. You can change that in OPU6. Sudhakar's reply will help you to schedule standard network.

Regards

Shrikant