Hello.
I am having an issue regarding the inherent and residual bar graphs in Risk Management 10.
I have loaded risks, and filled in the usual amount of information, but i get an error stating that "Some risks are hidden, because no risk level exists for them".
I have attempted to look and apply these risk levels, and I am sure that they are there, but if anyone knows exactly what information is needed, and what other things I need to look out for when this error
Hello Mayorline,
,
The risk level matrix is defined on basis of likelihood (probability) and impact level..
So when probability or impact are not defined in risk analysis the risk levels are also not calculated. Heatmap is shown on basis of risk level, so if the risk is not having any risk level it is not shown in heatmap and a warning message is displayed.Each risk displayed in the heatmap has to have Probability and Impactlevel and then accordingly Risk level calculated.
Please check in your system which analysis profile is being used. If the analysis profile is with automatic impact reduction OFF,the residual values in the risk analysis have to be maintained manually. (The analysis profile can be checked via transaction SM30 view GRRMVANALPROFILE, please notice the check box Impact reduction).The Residual Planned risk level is maintained only if the system is using analysis profile with impact reduction ON. This risk level type
represents ideal situation when all risk reduction are active and effective. It's something like risk level target we want to ideally achieve.
Thanks & Regards,
Chandani
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mayorline,
The message 'Some risk are hidden because no risk level could be found
for them' is OK. It's rather information message that there are some
risk without risk level (likely without analysis).
Furthermore, the SAP Notes recommended in this thread may help in providing more information regarding this message or you can follow few more in addition to them as given below:-
SAP Note:- 1670269
SAP Note:- 1679238
SAP Note:- 1662127
Best Regards,
Akhil Chopra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mayorline,
You may also follow the below steps to find the risks with unassigned levels-
1.Run transaction sa38
2.Enter GRFN_REPORTING_TEST and execute
3.Enter the report GRRM_HEATMAP
4.The result of this program displays all fields available for the
report and one of them is also risk ID
Best Regards,
Saksham
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can alos check the SAP note 1688820
regards,
Rajeshwari
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mayorline,
Kindly refer to the note 1708386.
Best Regards,
Saksham Minocha