Error in Budget transfer

Former Member
0 Kudos

Dear Experts,

I have two wbs elements say  A and B are in  same level .A having amount 3000 and B having amount 3000.now im going to tranfer 1000/- from A to B ..But it showing error...."

Overall budget less than overall release

Message no. BQ076"

.For this  i have tried unrelease the budget in cj32 ...Eventhough it is not taking ...Is there any seperate transaction code for unrelease the budget..?  ...kindly suggest ....

By

Suma

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

You have budgeted A & B Rs. 3000 each for (Overall/annual). Suppose you have released Rs.2000 from A & B (Overall/annual). Now, you have only Rs.1000 only in A to transfer to B. If you want to transfer Rs.2000 from A to B, you have to unrelease Rs.1000 from A and make sure that overall/annual budget available to transfer from A to B.

Go to CJ32-->select overall-->reduce released amount in A, select 2012-->reduce released amount (do Total up in both cases). Now, you can transfer amount from A to B.

Regards,

Murthy.

Former Member
0 Kudos

Thanks Murthy,

Im closing the thread..

by

Suma

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Suma,

Check below mentioned thread if can help you.

http://scn.sap.com/thread/1367780

Regards

Tushar

Former Member
0 Kudos

Hi Suma,

Check the actual and commitments.

You can unrelease the budget which is free.(budget 200, release 100, actuals+comm 75, then you can reduce the release to 75+ only )

After this you can transfer the budget.

There is no seperate t code(other than cj32) for this.

Regards,

Pranav

Former Member
0 Kudos

Hi pranav,

Thanks for your inputs....

In my scnario no  actual and no commitments yet to be posted ....

kinly suggest...

by

Suma

Former Member
0 Kudos

Hi Suma,

How much you has released out of 3000 against both WBS.

Hope u didn't forget to total UP.

Regards,

Pranav