on 06-21-2012 6:59 AM
Hi,
I have an requirement, when we transfer the project structure from MSP to SAP, the data in field (activity description) in MSP gets transfer to short text of network activity in SAP. Now the requirement is such that the data in the field (activity description) in MSP should get transfer to Long text of the network activity in SAP.
Kindly Let me know how is this possible?
Thanks & Regards,
Nitesh H Panchal
Hi nilesh,
Use data migration tool LSMW for uploading activity description of Network.
Regards,
Pranav