Static credit check: credit limit exceeded in assembly process

marcio_blos
Explorer
0 Kudos

Hi masters.

Anyone can tell me how works the automatic creation of network when credit limit is exceeded in sales order?

I think that the network isn't created.

How can I create the assembly order (Network) after the liberation of the sales order?

Regards

Marcio

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Marcio,

Please check in schedule lines of SO line item whether network is already created.

Regards

Shrikant

marcio_blos
Explorer
0 Kudos

Hi Shrikant,

The network wasn't created.

On VKM3, we aren't able to release the order.

All required fields are filled. This occurs only with assembly process.

marcio_blos
Explorer
0 Kudos

Hi folks;

I forgot to fill MRP controller in CN08.

It's working now!!!