Hi All,

When the AUC is created, only the cost center gets populated (pulled through from WBS element) and not the responsible cost center. This means I have to manually populate the responsible Cost center.

How do I make the responsible cost center to pull through from WBS element?

Thanks.

Regards

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Pls elaborate the problem