on 06-20-2012 11:06 AM
Dear colleague,
I have one EWM managed location which i need to discontinue and make it as WM managed as the process in that location are not much relevant to EWM activities.
Can you please help me guide how i can achieve it through configuration and what are the steps i need to follow.
Thanks
Sandeep Kumar
Hi Sandeep
Please follow below steps
Remove
>>Assign WM warehouse to EWM warehouse.
>>Defining Delivery Split by Warehouse Number
Logistics Execution → Shipping → Deliveries → Define Split Criteria for Deliveries → Delivery Split by Warehouse Number.
>>Generating the Distribution Model for ERP to EWM
Logistics Execution → Service Parts Management (SPM) → Integrate SPM with Other Components → Generate Distribution model ERP => EWM. Alternativerly, call transaction /SPE/OL19.
>>Maintaining Extended Warehouse Management-Specific Parameters
Logistics Execution → Service Parts Management (SPM) → Integrate SPM with Other Components → Maintain Extended WM-Specific Parameters.
>>Integration with Other mySAP.com Components>>Extended Warehouse Management>>Basic Settings for EWM Linkage>>Maintain Extended WM-Specific Parameters
>>Assign Warehouse Number to Warehouse Number of Decentralized SCM System
check above customization and check and Reply if it works as required.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.