Dears

I have a requirment like below,

When i create a PO to a vendre first time system need to
trigger a special inspectin plan for GR

if the above inspection plan in ok then for next PO i need to have a different inspection plan against GR

Is it possible to map this by using Supply Relationships

Pls tell me the detail step how we can assign different plan for different status


and aslo how it ppossible to cotrol PO QTY in status managment

Thanks in advance

Abu Fathima

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

1. You can assign the supply relationship status in QInfo record.

You can assign inspection type 0101 for model series ( initial pilot series  etc)

01  production series etc

Create different task list for different inspection type.( means in customization of these inspection type assign different usage)

2. Status mgt do not play any role in qty as such ,its quality info record"Qty release" tab which control qty in PO.

former_member223028
Participant
0 Kudos

Hi sir two clarification

1.So by using in quality info record we can not control the PO qty for pilot serios and production etc...

2.If we GR a PO quantity partially by two times then system changes the status in quality info recored .how we can control this, changing the status in Quality info recored for different PO only

Abu fathima

Former Member
0 Kudos

1.So by using in quality info record we can not control the PO qty for pilot serios and production etc...

- No

2.If we GR a PO quantity partially by two times then system changes the status in quality info recored .how we can control this, changing the status in Quality info recored for different PO only

- No again not std one.

may be you have to check the possibility of customizing a table where in you can have check in PO qty & status.

Answers (0)