cancel
Showing results for 
Search instead for 
Did you mean: 

Re-determine Requirement type on Sch Agree with document subsequent

Former Member
0 Kudos

Hello,

is it posible to re-determine Requeriment type on a Scheduling Agreement  item that already has a subsequent document?

Thanks!

Accepted Solutions (0)

Answers (1)

Answers (1)

Shiva_Ram
Active Contributor
0 Kudos

Do you mean you want to change item category in the scheduling agreement? If so, then make the quantity of the line item similar to the subsequent document and for balance add a new line and change the item category.

Regards,

Former Member
0 Kudos

Shiva,

I need to change Requirement Type (tab 'Procurement' - field VBAP-BEDAE).

The quantity on Sch Agreement and Outbound delivery is the same.

Do you know if it's posible?

Thx!

Shiva_Ram
Active Contributor
0 Kudos

I don't think it is possible, when subsequent document is created.

Note that the requirement type is determined based on the item category, MRP type and strategy type (in the material master) settings in t.code OVZI. So to change the requirement type either one of the parameter needs to be changed as per the setting in OVZI. If there is no subsequent document exists for an item, then using the above parameters you can change.

Regards,

Former Member
0 Kudos

That's what i thought.

thanks for your help Shiva.