Does anyone know why when I enter a value in a particular week in the Production Planned Key Figure in SNP and then hit the enter button, the value would jump to another weekly bucket (usually to the next week's bucket or two week's out bucket)?  Is it controlled by something in the Product Master?

Thanks for any insight.

Andrea

Accepted Solutions (0)

Answers (1)

Answers (1)

rajkj
Active Contributor
0 Kudos

Andrea,

Probably, there might be few activities that could not be completed in the same time period (cross-period activity). Please check your manually created planned order's start, end, and available times. Usually SNP displays the planned order based on it's available time.