Disallow to change inspection plan by QP01

Former Member
0 Kudos

Dear Experts,

we have removed authorization of qp02 (chnage inspection plan),

but user can change specification (inspection plan) by QP01.

how to disallow to user for change inspection plan by QP01.

Regards,

Yuvraj Dhotre

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

check authorization object-Q_ROUT in required user role. It should not have activity-02