Hi Experts,
I have configured the 'FM' module but i strucked up in few of the below requirements. Can anybody help me where can we do this below configuration?
1) My Client want to Enter the plan budget(initial Budget) in SAP System, and once it get approved by the manager it should update into SAP FM module as released budget. Can anybody guide me how or where(T-code) do we do the configuration?
2) In FMBBC we have option called "PREPOST". What is the functionality of this Option? What are the settings needs to be done to use this option.
Thanks in advance.
Regards,
FM USER.
help.sap.com
06-13-2012 6:43 AM
Hi
You can use budget release process, so that budget will be available after approval/release only.
IMG path is: Public sector Management-Funds management government-budget control system-definition of master data-budget releases.
If you want to control a budget entry with/without workflow connection using an approval procedure, then save the entry document by pressing the Prepost pushbutton.
You store budget temporarily that you want to process later by clicking on the pushbutton Held. The budget document receives a user-defined document number and is stored temporarily in your work center and not in the database.
Regards
Rao