Hi Experts,

In my PPDS planning board profile, i have set different colours for RESOURCE CHART and i have assigned in the product master extras tab. Now there are 2 products test1 and test2 for which same resource is used. I have assigned grey to test1 and assigned blue to test2. When i create order for test1 in the DSPB both the product chart and resource chart are displaying in Grey which is correct. But for test2 when i create orders, in the product chart it is blue but in the resource chart it is in someother colour which is not correct. The resource is respecting the colour for test1 but not for test2 even though the same resource is used. Any setting in resource chart? Pls let me know. Thanks

Shruthi

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Please check the Detailed Scheduling Planning Board Profiles Transaction  in   /SAPAPO/CDPSC2 for coulor for graphical display.

Please refer this link for details,

http://scn.sap.com/message/10525226#10525226

Regards,

R.Brahmankar

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Shruthi,

Please check if you have maintained any downtimes for the Resource. If Down time exsists then the period is blocked with a grey color.

Else then you normal resource background is white with blue order for Test2.