on 06-12-2012 6:04 AM
Dear Gurus,
How system calculates basic finish date in the maintenance order.
What is the configuration that i do for default current date as finish date.
I require basic finish date as my TECO date.Is it possible with standard SAP?
Pls suggest..
Thanks in adv
LAX.
hi
it calculates based on the hours you entered in the operation, breaks and capacity utilization specified in the work center capacity
while TECO you can specify the which date system should propose in IMG
regards
thyagarajan