Basic finish date

Former Member
0 Kudos

Dear Gurus,

How system calculates basic finish date in the maintenance order.

What is the configuration that i do for default current date as finish date.

I require basic finish date as my TECO date.Is it possible with standard SAP?

Pls suggest..

Thanks in adv

LAX.

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member187991
Active Contributor
0 Kudos

hi

it calculates based on the hours you entered in the operation, breaks and capacity utilization specified in the work center capacity

while TECO you can specify the which date system should propose in IMG

regards

thyagarajan