Transfering Phantom Material to Project from Material BOM

Former Member
0 Kudos

Hi All,

When i assign Phantom Material manually to the NWP/Activity system gives a message "if the items are to be relevant for procurement" but when i transfer a BOM (via t Code CN33) with Pantom material i am not getting the message and system is automatically not copying the phantom material to NWP/Activity.

Is there any config by which i can setup system so that system gives me the message when i transfer the Phantom Material via BOM  transfer transaction to NWP/Activity.

I want to Phantom material to be copied to Project via BOM transfer, any pointers will be helpful,

Warm Regards,

Jatinder

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member230675
Active Contributor
0 Kudos

BOM Transfer will happen only for the components not for the Header Material.

Please create a WBS BOM and maintain Phantom Materials as a component in that.