on 06-11-2012 6:46 AM
Hello,
I have One requirement..
I have Two Storage units(Handling Units)..say H1 & H2..
Hierarchy are..
H1
10 S1 quantity
10 S2 Quantity
H2
5 S1 Quantity
5 S2 Quantity
Now my requirement is to move 1 S1 from H1 to H2....
so the structure would be :
H1
09 S1 quantity
09 S2 Quantity
H2
6 S1 Quantity
6 S2 Quantity
And storage unit number which i am removing from H1 should be same while i am adding it into H2..
How to do this...
Help me out
thanks in advance...
hello..
I have solved it..
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi....
go to HU02....
then enter the handling units number into the first tab..pack material..
all existing HU..
H1
H2..
then press enter...then go to general overview...F8..
then u will get ur handling units...
now expand ur HU..
and click on Storage units which u want to move out from H1..
now there will be 3 Handling units...
H1,H2 and S1..
then double click(Select) on S1 and then H2..then go to pack option in the header...it will move the S1 into H2..
try this out..
Thanks