Dear All,
Can any body explain what is Difference between New start save to call and scheduled save to call in Maintenance Plan in sap?
Please explain with one example?
Regards,
Harsha.
Hi,
Suppose you have a maintenance plan with frequency is 3 months and the scheduling period is 12 months.
When you do the scheduling with start date as 01.03.2012
The scheduling result will be
01.06.2012 NEW START SAVE TO CALL
01.09.2012 SCHEDULED CALL SAVE TO CALL
01.12.2012 SCHEDULED CALL SAVE TO CALL
01.03.2013 SCHEDULED CALL SAVE TO CALL
If you save the scheduling, the NEW START SAVE TO CALL will be immediately converted in to work order. The SCHEDULED CALL SAVE TO CALL will wait for the next schedule
Hope this helps you
Regards,
Raj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
when you schedule the maintenance plan the first call generated will have NEW START SAVE TO CALL, where as for next call the status will be Scheduled call save to call
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
9 | |
9 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.