on 06-08-2012 8:18 PM
Hello All,
I have a scenario in which i am doing Sales Order Costing on each line items. But the issue is there are many line items on which we have to run Sales Order costing. Is there any possibility to run sales order costing on header level so that every line item will get its cost instead of running line by line. We are doing MTO scenario moreover Sales Order Variations happens most of the time in terms of BOM/Raw material new customer's requirement b4 production.
Kindly guide me what to do...
Regards
Hi,
It is not possible to run the cost estimate for all the line items at a time. We can run the cost estimate in the sales order itself by selecting the line item and go to 'extras' tab and click on costing. Or else you can use ck51n to run cost estimate line item wise.
thx
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Still waiting for the valuable answer ....
Best Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Still waiting for the reply. Need Help...
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi SD,
Actually the costing is run by FI Gouys But as per my knowledge we have to use CK11,CK24 and Ck40N.
you have to run the CK40N for main item i mean FG material and child parents costing also running.
when ever you didnt run the costing for materials by that time the billing document will not generated.
so please see above transactions
Thanks,
Naren
Dear,
The Costing job will be done by CO Consultant, we are only concerned about values.
Since you are asking about it, this can be achieved by CK11N and CK24 as the materials are few.
CK11N - Run the costing with correct costing variant and date structure and save it
CK24 - Mark it and release it. So that the problem will get solved. Costing in MTS and MTO scenarios will be done through CK40N, CK11N and CK24 only. Infact, all costing estimates.
Please be very careful and take the help of CO Consultant
Thanks