Control projects weekly in SAP PS

Former Member
0 Kudos

Hi Gurus:

I have a problem with the SAP PS module,  my company need to track weekly projects, I have seen the CJ20N, I can register the project there, but when I want entering the percentage of complete only appear monthly periods. How I can change the periods to let me enter the percentage to complete weekly?

Regards.

Carlos

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member230675
Active Contributor
0 Kudos

I think you are using Project Progress measurement method "Estimation" , In this method system will allow to enter POC per month as it is a standard method.

If you need to enter weekly then use "Develop Measurement Technique Enhancement"

Or simply update in the same monthly column every week with the new cumulative values.