Dear All,

Working on SCM 7.0

This is regarding the Schedule Lines , we have added the Standard Key Figure "Distr.Receipt(SL)" in planning Book , its having the category "BE".

When we create Schedule Lines in ECC , the schedule Lines are not updating in this Key Figure , But it is Updating in key Figure "Distr.Receipt(Plnd)"  whcih is having category "AG/BD/BE/EA/HG".

As the requirement is to get the Schedule Lines in seprate Key Figure and it will be used in Macro to add only "STO/Stock/Schedule Line".

Is there any way to handle this isslue ? why the schedule lines not updating in Key figure "Distr.  Receipt(SL)" ?

Is it possible to write a macro using Aux Ky Figure to get only "BE" category orders ?

Thanks in advance..

Rajesh

Accepted Solutions (0)

Answers (1)

Answers (1)

rajkj
Active Contributor
0 Kudos

Hi Rajesh,

Have you modeled off your planning area based on 9ASNP03?

Also ensure that 9APSHIPLP key figure is already added to the aggregates like 9AMALO, 9AMALA, etc.

The following SAP note might be useful to you.

https://service.sap.com/sap/support/notes/892123

Thanks,

Rajesh