on 06-06-2012 8:26 AM
Hi all,
I have a problem where inspection end date is not getting changed, it is reflecting the Insp.Start date. The lot was created on 01.06.2012 and UD against the lot was done on 06.06.2012, in QALS i find the inspection end date and doc. posting date as on 01.06.2012. I dint find a date 06.06.2012 in QALS where the actual UD was done on this date.
Thanks in advance,
Prashant Pillai
Hi Prashant,
Inspection end date need not be same as UD given date. Calculation of inspection end date depends upon aveage inspection duration which you maintain in material master in QM view against specific inspection type.
You can manually also change this date in QA02 BUT before UD.
UD given date is stored in QAVE while in QALS you can find next and start inseption date.
Regards,
Anand
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
You will find it in QAVE table.
Manish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.