Hi
One of my user has such a long scheduling period in their maintenance plan master which made it beyond our caledar 31.12.2030.
Now when I trys to IP10 I gets error IP889 (error description below).
My question is how to fix the master data, I have remove the sceduling operiod values but still getting the same error.
Diagnosis
During scheduling of the maintenance plan, the planned date was set to
00.00.0000.
This error can occur, if, for example, the cycle for the planned
schedule is too big (offset) means that the planned date is actually
after the 31.12.9999.
Procedure
Check the master data of the maintenance plan to ensure that no date is
calculated after the 31.12.9999.
I have fix the issue by adjusting the annuak performance of the measurement point.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Aqva ,
what is the maintenance frequency in your order ? and what other parameters you have entered lke start of cycle , scheduling period , tolerance etc ?
REgards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.