Scheduling a Job on daily basis but not on month end

Former Member
0 Kudos

Hi Experts,

We have a client requirement of scheduling a job on daily basis but job should run at month.

I was trying to schedule it using factory calender but it doesnot help.

How to schedule this job such that automatically job donot get executed at month?

or i have to manually delete the job at month end .

I have ECC 6.0 EHP5 system

Please provide a solution.

Regrads

Deepak

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Deepak,

As far as I know that you can't exclude a day from the schedule, if you don't use factory calendar. If it is a customer program, developer can modify it to check the end of month in the initialization and avoid to run at the end of the month.

Best regards,