on 06-01-2012 7:12 AM
Dear Experts,
My client has Dynamic credit check policy.
Let say
We have a SO for 10 MT on 27th May 2012 .Now we want to create delivery for 5 MT. Due to Dynamic Credit check we are not able to create Delivery on 27th May 2012. But after releasing the SO through VKM4 we are able to create Delivery,PGI & Invoice on 27th May 2012.
But problem arise on next day i.e 28th May 2012. If we want to create the delivery with reference to the above SO then again we have to release the SO through VKM4.
We are getting the below error
Subsequent function '' not possible due to a credit block"
Message no. V1849
Our requirement is after releasing the SO it will not block for ever. What exactly we have to do for the particular case.
But why after releasing the SO we are not able to create the delivery on next day onward. Why the particular SO is releasing only for one day.
Regards
Santanu
Hi Giri,
i think you were set on the date 27th may 2012 for that transaction.When ever expired that date automatically that transaction blocked .So please change the date 27th may to 28th may ok.
Thanks,
Naren
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Santahu,
Request you not to create Multiple threads for same question.
You have created a thread 2 days back with same question: http://scn.sap.com/thread/3183939 & have received couple of suggestions there.
Please close either one of the thread & continue the discussion in only one thread.
Thanks,
Jignesh Mehta
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.