on 05-31-2012 10:58 AM
hi ,
At presenet we have overall budgeting in our system. We want to go for anuual budgeting for existing projects also.
Kinldy let me know how can i transfer my budget on existing project which are released as overall to anuual values.
What steps are requiered to do this in current projects.
Regards,
Kalpesh
You only have to change your budget in CJ30 and now you should distribute the budget based on the period.
I dont see any problem here. Let me know if you encounter any problem.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kalpesh,
The way you have created overall budget(cj40->cj30->cj32) in system need to be followed again. While repeating please choose period 2012 instead of overall from dropdown menu.
Please assign points if helpful.
Regards,
Pranav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.