on 05-30-2012 5:43 PM
Hello Experts,
Here is a scenario:
2 landscapes (assigned to the one ChaRM Project) will look like that:
What is required:
Is it really possible with ChaRM 7.1???
Thank you.
Hi M M,
Hope that helps,
Michael
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi M M,
just one note about topic 3) If cCTS is integrated into ChaRM this will be possible as well. In a the near future release.
best regards,
Michael
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Michael,
Thanks a lot for your help!
Few more questions (please find my comments below):
Create Urgent Change and move TRs ONLY to PRD(1) : DEV(1) -> Q&A(1) -> P-PRD(1) -> PRD(1) -> possible, just select the iBase of prod1 system and it's transported to this track only.
Then move TRs which are already in PRD(1) to PRD (2) : DEV(1) -> Q&A(2) -> P-PRD(2) -> PRD(2) using !!!the same!!! Urgent Change -> Possible with report Report /TMWFLOW/SCMA_BTCH_SYNC_TEST > my client doesn’t like this option and insisted to have sort of approval mechanism for PRD(2) system as well as for PRD(1). I know it sounds strange, but this is my client’s requirements. Is any way to use the same UC while running the report? I’m not sure...
Create Normal Change for both landscapes, and move TRs simultaneously in both landscapes. -> not possible simultanously , you can distribute to multiple test systems but not like this. Why do you want it in the second prod system? > this is my client’s requirement, I’m afraid.
Is is more kind of a retrofit or a parallel system with the same stack? There are parallel SAP ECC systems used for 2 geographical regions.
This would be two normal changes under one RfC with different iBases of both prod systems which means the change (the Request for Change) is the hook for both systems but you would have to trigger the import manually or via batchground job.
Thanks & regards,
MM
Hi MM,
sorry to say, there is no authorization procedure for the report that I know of. It would involve customer development to maybe integrate an approval workflow in the report. Or to enhance the task list report for manual import.
For 3.) Then you have to wait for cCTS Integration with ChaRM, right now it's in pilot phase, it's planned for SP08 global avaibility (no gurantee here).
best regards,
Michael
Hi,
we have exactly the same scenario (one logical development system which feeds two productive landscapes because of region & timezone: one PRD system for Europe and one for APAC).
Our solution for the normal change was to switch the "Tested OK" approval from a PPF action to an approval assignment block with an approval procedure containing the functions "Tester" and "Parallel Tester". Only when both regional business departments give their ok the change goes into both production systems
User | Count |
---|---|
93 | |
10 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.