how you will identify either backward or forward scheduling takes place in sales order

Former Member
0 Kudos

Dear gurus

       how we will identify either backward or forward scheduling takes place in sales order ?

thank you so much

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello Venu,

You can check if the system has carried out backward scheduling or forward scheduling in sales order.

As told by experts earlier, its done by Availability check.

Just go to the schedule lines in the sales order.

Check whether the delivery date and confirmed quantity date in item data for schedule lines.

If the confirmed quantity date is same with the delivery date, then the system has carried out backward scheduling

If the confirmed quantity date is ahead to the delivery date then system has carried out forward scheduling.

Hope this helps

Thanks and regards

Amit

Answers (3)

Answers (3)

jignesh_mehta3
Active Contributor
0 Kudos

Hello,

A very simple mathod of knowing whether Backward or Forward Schedulling has taken place in your Sales Order:

1. If the Schedule Lines Delivery date is same as your Requested Delivery Date, then if is Backward Schedulling.

2. If the Schedule LInes Delivery Date is in future (as compared to Requested Delivery date) then it is forward Schedulling.

Thanks,

Jignesh Mehta

former_member184065
Active Contributor
0 Kudos

Hi venu,

The Backward or Forward scheduling is identified by Availability check.When ever we have to maintain the availability check for  materials(finished goods)by that time we have to raise sales order for that materials.so if there is available that materials for sufficiant for that sales order ok fine this carried out by forward scheduling i mean if that material availability date is flase between the purchase order date and delivery date ok fine.But some situations this is not possible why because that materials not available by that time the system assume other delivery date based on availability check.

Material availability =forward and not availability =back ward depends on Availability check

Thanks,

Naren

former_member211616
Active Contributor
0 Kudos

Hi Venu ,

Hear by i am attached a link http://www.slideshare.net/NareshGupta5/what-is-forward-and-backward-scheduling

please see to it will help u out to identify the backward and forward scheduling

Hope it will help u out

Regards

Ramesh

Former Member
0 Kudos

If system confirms requested delivery date than its a backward schedulin.

If system propose new delivery date than its a forward scheduling.

Can refer link :--

http://help.sap.com/saphelp_erp2004/helpdata/en/dd/5607e7545a11d1a7020000e829fd11/content.htm

http://scn.sap.com/thread/1941858

Thanks

Rajesh