We have created a project, so say one year Jan 2012- Dec2012 and staffing is completed in cProject, at a later stage we change the period from Jan2012-Dec2012 to Jan2012-Sep2012, Surprisingly in Financial Planning tab the cost is still being displayed in last Quarter.
I tried debuging, and as to what I got is two FMs are called twice.
1. /RPM/ITEM_MODIFY
2. /RPM/SAVE_CHANGES
I've trying to get throught this issue, but all efforts have been invain. Any help would be highly appreciated.
Hi,
Per my understanding, auto re-distribution of planned values to new planned dates is not available.