on 05-25-2012 11:07 AM
Hi,
the changes made in PDS_MAINT for SNP PDS such as proc priority, period factory etc is not getting transfered to PDS in APO.
The IM for PDS is active.
Please let me know if i need to do some more setting to make the changes of PDS get transfered to APO.
Thanks
Abhi
Hi Abhi,
You can run report RIMODINI in ECC to transfer the PDS to APO again.
Claire
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Abhi,
Some questions:
1. Do you get the same behavior with all PDS's?
2. Is the PDS (production version) in more than one integration model?
3. Are you by any chance using recursion (component and header material are the same)?
4. Is the original PDS in APO? Does it match the ECC data?
5. Is this for a PP/DS PDS or an SNP PDS?
6. What version and service pack level of ECC and SCM are you using?
I assume you checked the change transfer box in CURTO_CREATE.
Best regards,
Mike
Hi Mike,
Thanks for your reply, it helped me as a guide in checking different setting for analysing the issue.
Actually i wanted to change the subcon PDS and there is a radio button "subcontractor maintenance" in PDS_MAINT selection screen and i was not selecting this option.
Now i can see the PDS change transfered to APO for subcon PDS.
Thanks all again for your help
Regards
Abhi