Changes made in PDS_MAINT not transfered to PDS in APO

Former Member
0 Kudos

Hi,

the changes made in PDS_MAINT for SNP PDS such as proc priority, period factory etc is not getting transfered to PDS in APO.

The IM for PDS is active.

Please let me know if i need to do some more setting to make the changes of PDS get transfered to APO.

Thanks

Abhi

Accepted Solutions (0)

Answers (1)

Answers (1)

claire_yang
Contributor
0 Kudos

Hi Abhi,

You can run report RIMODINI in ECC to transfer the PDS to APO again.

Claire

Former Member
0 Kudos

Hi Claire,

I have tried that but somehow the changes are not getting transfered to APO.

Regards

Abhi

Former Member
0 Kudos

Hi Abhi,

Try running transaction CURTO_CREATE to transfer the changes to the PDS.

Best regards,

Mike

Former Member
0 Kudos

Hi Mike,

I have tried that as well.

There is one interesting observation when i try to send changes in PDS to APO, I get a messase " No transfer-relevant data found ". though i have changed data in PDS_maint.

Former Member
0 Kudos

Hi Abhi,

Some questions:

1.  Do you get the same behavior with all PDS's?

2.  Is the PDS (production version) in more than one integration model?

3.  Are you by any chance using recursion (component and header material are the same)?

4.  Is the original PDS in APO?  Does it match the ECC data?

5.  Is this for a PP/DS PDS or an SNP PDS?

6.  What version and service pack level of ECC and SCM are you using?

I assume you checked the change transfer box in CURTO_CREATE.

Best regards,

Mike

Former Member
0 Kudos

Hi Mike,

Thanks for your reply, it helped me as a guide in checking different setting for analysing the issue.

Actually i wanted to change the subcon PDS and there is a radio button "subcontractor maintenance" in PDS_MAINT selection screen and i was not selecting this option.

Now i can see the PDS change transfered to APO for subcon PDS.

Thanks all again for your help

Regards

Abhi